CPM
began working for the District in preparation for a $101 million
local bond for new construction and renovation. The District hired
CPM to review program and project budgets and schedules, to help
bring a realistic, credible plan for capital outlay expenditures
to the voters. After the bond passed, CPM was awarded contracts
to provide program management including strategic planning, monitoring
and tracking of program and project budgets, reporting to the
citizens’ oversight committee, developing design standards,
and project management of design phase through bid and award.
|